First published: 18 June 2026
| Publish notice of intention to commence plan making | 18 June 2026 |
| Scoping consultation start / end | 24 June – 5 August 2026 |
| Gateway 1 | 18 October 2026 |
| Plan content and evidence start / end | 30 November 2026 – 15 February 2027 |
| Gateway 2 advice sought | 1 July 2027 |
| Gateway 2 advice published | 12 August 2027 |
| Proposed plan consultation start / end | 1 October – 10 December 2027 |
| Gateway 3 advice sought | 1 June 2028 |
| Gateway 3 advice published | 13 July 2028 |
| Plan submitted for examination | 1 August 2028 |
| Examination recommendations published | 1 February 2029 |
| Plan adopted | 1 March 2029 |
Approved Data Standard
The council must follow the approved data standard to publish our local plan timetable so that we meet the requirements of the Planning Data (England) Regulations 2026. This data is provided under the Open Government Licence and can be downloaded here in CSV File format: