A65 Kirkstall Road Quality Bus Corridor scheme update

Red Surfacing & Planting May 2012
Red Surfacing & Planting May 2012
New Pedestrian Island April 2012
New Pedestrian Island April 2012
Existing Road Being Removed March 2012
Existing Road Being Removed March 2012
New Bus Shelter March 2012
New Bus Shelter March 2012
New Road Layout Angel Halls January 2012
New Road Layout Angel Halls January 2012
New Planting Outside Fire Station November 2011
New Planting Outside Fire Station November 2011
New Road looking towards The Viaduct October 2011
New Road looking towards The Viaduct October 2011
Planting at Willow Road Viaduct July 2011
Planting at Willow Road Viaduct July 2011
New Traffic Island at Fire Station May 2011
New Traffic Island at Fire Station May 2011
Widening at Fire Station April 2011
Widening at Fire Station April 2011
Willow Road Junction January 2011
Willow Road Junction January 2011
South Side Widening November 2010
South Side Widening November 2010
Viaduct over the A65
Viaduct over the A65
Preparing for new retaining walls outside Angel Halls of Residence
Preparing for new retaining walls outside Angel Halls of Residence
Preparing for new road layout at Willow Road junction looking East
Preparing for new road layout at Willow Road junction looking East

A65 Kirkstall Road Quality Bus Initiative - Scheme Update 25 – May 2012 *UPDATE* 

Traffic Management 

Commercial Road - Beecroft Street to Woodside View – The current traffic management arrangement will remain in place until 23 May 2012. Traffic will then be moved to the north side of the new pedestrian refuge islands. This is to allow the completion of the southern footways and the new carriageway. This arrangement of one lane in each direction will be in place until 25 June 2012.

Willow Road Junction to Northern Snooker Centre – City bound traffic – Red surfacing works are now being carried out on the inbound bus lane. Traffic has now been moved onto the general traffic lanes (see Plan 30 – May 2012).

City Centre to Willow Road Junction – Outbound traffic – Southern footway works are ongoing and to enable the works to be carried out safely, traffic has been moved towards the central reservation (see Plan 30 – May 2012).

Day works 

Studio Road (Between Cavendish Street and Kirkstall Road) – 23 May 2012 and 24 May 2012 - Traffic signals will be in operation to allow carriageway works to take place. Minor delays are expected.

Immigration Centre to Birfed Crescent – 6 June 2012 to 8 June 2012 –The new outbound carriageway will be surfaced during the school holidays. Minor delays are expected.

Night works 

Willow Road Junction – 21 May 2012 for approx. 2 weeks (19:00 – 05:00) – Traffic lane and road closures will be in place to allow carriageway surfacing works. Diversions will be in place during road closures and journey times will be increased. Phase 1 road closures will take place on 22, 23 and 24 May 2012 (see Plan 31 – May 2012). Phase 2 road closures will take place on 22, 23 and 24 May 2012 (see Plan 32 – May 2012). Phase 3 road closures will take place on 28 May 2012 (see Plan 33 – May 2012) and Phase 4 road closures will take place on 29, 30 and 31 May 2012 (see Plan 34 – May 2012).

Studio Road (Between Cavendish Street and Kirkstall Road) – 22 May 2012 and 24 May 2012 (20:00 – 05:00) – Overnight carriageway surfacing works will be taking place. Diversions will be in place and minor delays are expected (See Plan 35 – May 2012).

Birfed Crescent to Sacred Heart School – 11 June 2012 to 15 June 2012 (22:00 – 05:00) – Final surfacing works will take place on the outbound carriageway and footways. Traffic lights will be in operation and delays are expected.

Further traffic management and closure updates will be posted on this page as they become available. Dates given for works and closures are approximate and weather dependent.

News 

Leeds City Council has landscaping teams already on site planting hundreds of new plants, shrubs and trees in, wherever possible, the completed sections of the construction work. On completion of the A65 Quality Bus Initiative Project the landscaping will enhance and add colour to the Kirkstall Road corridor.

The latest scheme plans can be found on our A65 Quality Bus Corridor web page.